Plant engineering · design → build → commissioning → operation

01

Configuration that works at this scale

SectionTypical equipmentEngineering note
Receiving & mixingConcrete reception bay, loader, mixer, amendment dosing by volumeKeep it under cover; a wet winter reception bay is where small plants lose their moisture balance
FermentationCovered windrow with a self-propelled turner, or a shallow groove with a small turnerThree lanes of 8–12 m are usually enough; do not under-size the aisle for loader access
Grinding & screeningSemi-wet material crusher plus rotary screenerOne crusher and one screener can serve both powder and, later, a granulation section
BlendingHorizontal or drum mixer with volumetric or small batching scaleFormulation flexibility is the main commercial advantage of a small plant
BaggingSingle or double bucket packing scale, 10–50 kg, manual stitching or sealingSemi-automatic bagging is normally the right choice at this scale
StorageCovered product store for 2–4 weeks of outputProduct moisture regain in an open store is the most common quality complaint
02

Footprint and utilities

For 1–3 t/h the fermentation area usually dominates: three windrow lanes of 10 m × 25 m with turning aisles occupy 1,000–1,500 m² on their own. The processing building can be compact — 18 m × 30 m is a comfortable envelope for crushing, screening, mixing and bagging with room for a future granulator — and the product store another 300–500 m².

Utilities are modest: 60–200 kW connected load, water for moisture correction and dust suppression, and, if the plant later adds drying, a fuel supply. The item to get right from day one is drainage. Small plants are frequently built on a flat slab with no falls, and then spend every rainy season with leachate standing where the loader has to work.

03

Labour and the shift pattern

  • Receiving and mixing — one loader operator who also controls amendment dosing.
  • Fermentation — one operator on the turner, part-time; the discipline is in the records, not in the hours.
  • Processing and bagging — two to three operators on the line.
  • Maintenance — one mechanically capable person, even part-time, who does daily checks and lubrication. Small plants fail on bearings, belts and chains far more often than on process design.
  • Quality — one person responsible for daily moisture and temperature records and for bag weight checks.
04

Quality control without a laboratory

A small plant cannot justify a laboratory, but it can control the four variables that decide whether customers come back: moisture of bagged product (oven or moisture meter, one measurement per batch), temperature in the pile (probe, three depths, three times a week), screening (visual check on the reject stream, weighed once a week), and bag weight (check-weigh five bags per shift). Record them on one sheet per day. Plants that keep this record for two seasons know their process; plants that do not spend that time guessing.

05

Planning the expansion at design stage

  • Reserve the footprint for a granulation and drying building beside the processing building, with the height and the lifting access designed in.
  • Cast the power provision for the future connected load; a transformer upgrade later is a utility lead time, not a purchase.
  • Lay out fermentation so a fourth and fifth lane can be added without moving the turner route.
  • Leave the bagging bay long enough for an automatic bagging and palletising line, with the conveyor route marked.
  • Design the reception bay for the truck size you will use in five years, not the one you use today.

Plan a small plant

Tell us the feedstock available per day and the bag size you want to sell; we return the configuration, the footprint and the equipment scope.

FAQ

Plant engineering questions

What is the smallest viable organic fertilizer plant?

Around 0.5 t/h of finished powder, which corresponds to roughly 10–15 t/day of fresh manure. Below that, a farm usually composts and sells bulk material rather than operating a bagging plant.

Do I need a granulator in a small plant?

Not at the start. Powder is simpler, cheaper and adequate for many local markets. The argument for granules is transport distance and retail presentation — so plan the space for a granulator, but sell powder first if your market accepts it.

Can a small plant handle both manure and green waste?

Yes, and mixing them usually improves the process, because green waste supplies carbon and manure supplies nitrogen. The design basis must state the shares, because the moisture and C/N of the mix decide the fermentation regime.

How long does it take to build a small plant?

Typically three to five months from design approval, including local civil works. Fabrication of the compact equipment set is usually the shorter part of the programme.

Send us your design basis

Tell us the feedstock, the daily tonnage and the product you want to sell. The engineering team replies with the plant configuration, the equipment scope and the information we still need before layout drawings start.

  • Feedstock profile — type, moisture, contamination, seasonal peaks
  • Capacity — t/day fresh material or t/h finished fertilizer
  • Product — powder, granules, bagged retail, bulk compost
  • Site — available area, power supply, water, access road