Plant engineering · design → build → commissioning → operation

01

The design basis document

The design basis is one or two pages that fix the project. Everything after it — equipment sizes, building dimensions, power demand, price — is a consequence. When a plant later underperforms, the cause is almost always found in this document rather than in the machines.

  • Feedstock table: types and shares, tonnes per day average and peak, moisture, bulk density, C/N ratio, pH, contamination and delivery method.
  • Product specification: form (bulk compost, powder, granules, blend), target moisture, granule size range, bag size, and any labelling or registration requirement.
  • Climate: minimum winter temperature, rainfall, wind direction relative to neighbours, and whether the plant will run year-round or seasonally.
  • Site data: area and shape, ground bearing capacity, flood level, power supply and transformer capacity, water source, drainage outlet and access road.
  • Operating assumptions: shifts per day, labour available, automation level, and whether the customer will operate the plant or contract it out.
02

Mass and moisture balance — the sheet that decides the plant

StreamBasisWorked example (medium plant)Why it matters
Fresh feedstock int/day at received moisture120 t/day at 65% moistureSets receiving bay, mixer and loader duty
Dry matter int/day42 t/dayThe only mass that can become product
Amendment addedt/day18 t/day of dry bulking agentAdjusts C/N, moisture and porosity
Fermentation loss15–30% of dry matter≈ 9 t/day as CO₂ and water vapourDecides cured tonnes available to process
Screening rejects5–12%≈ 2.6 t/day returned to fermentationDecides internal recirculation and buffer size
Drying evaporationonly on granular lines≈ 6 t/day of waterDecides dryer size, fuel and air volume
Finished product outt/day and t/h≈ 40 t/day, 5 t/h over one shiftSets bagging rate, storage and dispatch

Figures are illustrative of the method, not a quotation. Every plant is balanced from its own feedstock analysis and moisture data.

03

Capacity sizing: which machine sets the line rate

A line is a chain, and the design rate is set by the narrowest link — but the narrowest link is different at different points in the process. In fermentation, the constraint is residence time and volume. In grinding and screening, it is the throughput at the required fineness and moisture. In granulation, it is the granule formation rate at the target size distribution. In drying, it is evaporation capacity at the inlet moisture you actually achieve after granulation — a number that is routinely 5–10 percentage points worse than the design assumption.

We therefore size every step with a stated duty margin and record it in the equipment schedule: grinding at 1.2× line rate, granulation at 1.1×, drying on the worst credible inlet moisture, screening at 1.3× with recirculation, and bagging at 1.2×. A line that is uniformly oversized wastes capital; a line that is uniformly equal to the nominal rate will run at 70% of design output for its whole life.

04

General arrangement and 3D design

The general arrangement is where plant design meets reality: loader turning circles, delivery truck access, bay wall heights, the height needed for a dryer and cooler in series, maintenance access to the granulator, the position of the control room within sight of the line, and the walk an operator takes to check the fermentation temperature at both ends of the bay at 6 a.m.

We issue the plan and elevation drawings together with a 3D model, because height conflicts are the most expensive mistakes in fertilizer plants: a dryer that cannot be lifted into the building it was designed for, a bucket elevator whose discharge height was taken from a catalogue rather than from the drawing, or a dust-collection duct that ends where a roof truss begins.

05

Utility and control design

  • Power — connected load per equipment group, starting current for the largest motor, transformer sizing, power factor correction and the voltage and frequency variants common in export destinations.
  • Thermal — hot air generator or hot water selection, fuel storage and safety, duct sizing, temperature control loop and exhaust treatment on granular lines.
  • Water — process water for moisture correction, dust suppression, cleaning and, where required, leachate recirculation instead of freshwater.
  • Compressed air — cylinders, valves and dust-collector pulse cleaning, with the dew point and consumption shown per consumer.
  • Extraction — local dust capture at grinding, screening and bagging, general ventilation in the processing building, and odour extraction with biofilter or chemical scrubber at the fermentation building.
  • Control — local panels plus a central control philosophy that states what is interlocked, what is monitored and what is recorded; instrumentation is chosen to be maintainable locally rather than impressive on paper.
06

Design review gates

  1. 01

    Gate 1 — design basis approval

    Customer confirms feedstock data, capacity and product specification in writing before process design starts.

  2. 02

    Gate 2 — process and mass balance approval

    Streams, losses and equipment duties reviewed; changes after this gate alter equipment sizes and price.

  3. 03

    Gate 3 — layout freeze

    General arrangement approved against the actual site survey, including building and civil interfaces.

  4. 04

    Gate 4 — pre-fabrication review

    Final equipment schedule, drawings and control philosophy confirmed; fabrication release.

07

Drawings issued at each design stage

General arrangement drawing of an organic fertilizer plant
General arrangement drawing: equipment sequence, capacities and buffer volumes at each step.
3D model of an organic fertilizer production plant
3D plant model used to check building height, lifting access and maintenance space before fabrication.

Start with the design basis

Send your feedstock data and target product. We prepare the design basis and the mass balance outline before any equipment discussion.

FAQ

Plant engineering questions

What do you actually need from me to start the design?

Feedstock type and daily tonnage (with peaks), a moisture figure or a sample, the product you intend to sell and its packaging, the site area and a site plan, your power supply, and the climate at the site. A phone photo of the feedstock pile and one of the site are genuinely useful.

Can you design from a capacity I already fixed?

Yes, but we will still check it against the feedstock supply. If a 10 t/h plant needs more fresh manure than the region can deliver every day of the year, the design basis will show that before fabrication rather than after commissioning.

Do you provide drawings for the civil contractor?

Yes — plot plan, foundation and plinth drawings with load data, drainage and hardstanding requirements, building envelope dimensions and utility interface points. Local contractors work from these directly.

How long does process design take?

Typically three to six weeks from an agreed design basis to an approved layout for a medium plant. Innovative feedstock or an unusual site extends stage two, because more of the balance has to be estimated rather than measured.

Send us your design basis

Tell us the feedstock, the daily tonnage and the product you want to sell. The engineering team replies with the plant configuration, the equipment scope and the information we still need before layout drawings start.

  • Feedstock profile — type, moisture, contamination, seasonal peaks
  • Capacity — t/day fresh material or t/h finished fertilizer
  • Product — powder, granules, bagged retail, bulk compost
  • Site — available area, power supply, water, access road

Prefer to talk first? WhatsApp +86 182 0399 3035 or email [email protected].

We use your details only to answer this enquiry. No newsletter, no third-party sharing.

WhatsApp
Request a proposal WhatsApp